OCEAN DEE

The work conducted on board the Ocean Dee involved separating the ship’s own fuel system from the cargo fuel system. The Navaleva team proposed modifications to the existing installation, coordinated the solution with the classification society, oversaw the execution of the work, and obtained approval for the system, securing the vessel’s new IOPP certificates within 10-12 days.
This involved the following:
  • Modification of the fuel pipelines for five tanks.
  • Modification of the vent piping for five tanks.
  • Renovation and required modifications in the accommodation area affected by the works.
PLACE
Port of LAS PALMAS DE GRAN CANARIA / SPAIN